鎴戝叕鍙告壙寤虹殑灞变笢鐪佹祹瀹佸競鍏栧窞鍖虹敓娲诲瀮鍦剧剼鐑у彂鐢甸」鐩儫姘斿噣鍖栧伐绋嬩簬2022骞8鏈5鏃ラ€氳繃72+24灏忔椂璇曡繍琛屻€
The flue gas cleaning (FGC) project undertaken by Huaxing East for the municipal waste incineration plant in Yanzhou Jining, Shandong passed the 72 + 24 hours trial operation on August 5, 2022.
璇ラ」鐩缓璁炬棩鐒氱儳澶勭悊鍨冨溇1500鍚紝骞村鐞嗛噺涓54.75涓囧惃锛岄厤32 MW锛1脳20MW+1脳12MW锛夋苯杞彂鐢垫満缁勩€傜儫姘斿噣鍖栭噰鐢ㄢ€滅倝鍐匰NCR锛堝翱绱)锛堥潪鎴戝徃鍚堝悓鑼冨洿鍐咃級锛嬪崐骞叉硶(娑堢煶鐏版祮娑)锛堥潪鎴戝徃鍚堝悓鑼冨洿鍐咃級锛嬪共娉(娑堢煶鐏板柗灏)锛堥潪鎴戝徃鍚堝悓鑼冨洿鍐咃級锛嬫椿鎬х偔鍠峰皠锛堥潪鎴戝徃鍚堝悓鑼冨洿鍐咃級锛嬭寮忛櫎灏樺櫒锛堥潪鎴戝徃鍚堝悓鑼冨洿鍐咃級+SGH+SCR锛堝翱绱狅級+鍌寲鍓傦紙涓夎彵閲嶅伐锛夆€濈殑澶勭悊宸ヨ壓锛屼负鎴戝徃EP宸ョ▼銆
The daily capacity of the plant is 1500 tons, the annual treatment capacity is 547,500 tons. A set of 32 MW (1脳20MW+1脳12MW) steam turbine generator is equiped. FGC adopts the process of SNCR with urea (not in Huaxing scope) + semi-dry with slaked lime slurry (not in Huaxing scope) + dry with slaked lime injection (not in Huaxing scope) + activated carbon injection (not in Huaxing scope) + bag filter (not in Huaxing scope) + SGH + SCR with urea + Catalyst (MHI). It is an EP project of Huaxing.
鐩墠鍗庢槦涓滄柟鍦ㄥ北涓滅殑涓氱哗娑电洊鍖呮嫭锛氳鍩庛€佹綅鍧婁竴鏈熴€佷簩鏈熴€佹綅鍧婇珮瀵嗐€佺墴骞炽€佹嘲瀹夈€侀珮瀵嗐€佹穭宸濄€佷复娌備簩鏈熴€佸皬娑цタ銆侀粍宀涖€佷复娣勪竴鏈熴€佷簩鏈熴€佷复娌傚叞灞便€佹矀姘翠簩鏈熴€佹枃鐧汇€佽幈瑗裤€佸痉宸炪€侀緳鍙c€佹矀婧愩€佹槍涔愩€佸晢娌炽€佸厲宸炪€佹灒搴勩€佸彴鍎垮簞銆佺珷涓樹簩鏈熴€佽幈宸炵瓑澶氫釜椤圭洰銆
The achievements of Huaxing in Shandong include Zhucheng, Weifang phase I & II, Weifang Gaomi, Muping, Tai'an, Gaomi, Zichuan, Linyi phase II, Xiaojianxi, Huangdao, Linzi phase I & II, Linyi Lanshan, Yishui phase II, Wendeng, Laixi, Dezhou, Longkou, Yiyuan, Changle, Shanghe, Yanzhou, Zaozhuang, Taierzhuang, Zhangqiu phase II, Laizhou, etc.