我公司承建的四川省巴中市垃圾点火发电项目二期烟气净化工程于2022年5月15日通过竣工验收。
The flue gas cleaning (FGC) project for Bazhong waste-to-energy plant Phase II undertaken by Huaxing East passed the completion acceptance on May 15, 2022.
该项目一期工程已建成投运。本期为二期工程,,,拟建设规模为日处置生涯垃圾600吨,,,配置1台600t/d机械炉排炉和1台15MW凝汽式汽轮发电机组。烟气处置选取SNCR+旋转喷雾半干法+干法消石灰喷射+活性炭喷射+布袋除尘器+飞灰输送、贮存及不变动工艺,,,为我司EPC工程。
The Phase I of the plant has been completed and put into operation. Phase II of the plant will construct a 600 t/d mechanical grate and a 15 MW condensing steam turbine. The FGC will apply SNCR + rotary spray semi-dry + slaked lime injection dry + activated carbon injection + bag filter + fly ash conveying, storage and stabilization process. It is an EPC project of Huaxing East.
伟德国际官网东方在四川省的业绩涵盖蕴含:邓双、金堂、隆丰、资阳、巴中、广元、宣汉、自贡、中江、广安、宜宾等多个项目。
Huaxing East's achievements in SiChuan Province include: Dengshuang,Jintang,Longfeng,Ziyang,Bazhong,Guangyuan,Xuanhan,Zigong,Zhongjiang,GuangAn,Yibin etc.