我公司承建的山东省商河县生涯垃圾点火发电项目烟气净化工程于2021年11月19日开工建设!。
The flue gas cleaning (FGC) project contracted by Huaxing East for Shanghe waste-to-energy plant at Shandong Province started construction on November 19, 2021.
工程整体成效图
该项目总处置规模2X500 T/D,,本期建设1台500 T/D炉排炉式垃圾点火炉和1台额定12 MW的凝汽式汽轮机和1台12MW发电机组!。二期增长1台500吨的机械炉排炉,,配置1台12MW汽轮发电机组!。烟气处置选取SNCR+旋转喷雾半干法脱酸+NAOH喷射系统(垂危)+干法喷射+活性炭吸附+袋式除尘器+飞灰输送、、贮存及不变动工艺,,为我司EPC工程!。
The total capacity of the plant is 2X500 T/D. In this period, a 500 T/D grate furnace type incinerator, a condensing steam turbine rated at 12MW, and a 12MW generator set will be constructed. In phase II, a 500-ton mechanical grate furnace and a 12MW turbine will be added. FGC applied SNCR + rotary spray semi-dry deacidification + NAOH injection system for emergency + dry injection + activated carbon adsorption + bag house filter + fly ash conveying, storage and stabilization process. It is an EPC project of Huaxing East.
伟德国际官网东方在山东省的业绩涵盖蕴含:兖州、、德州、、定陶、、高密、、黄岛、、莱西、、莱州、、鹤壁二期、、鹤壁兰山、、临淄一期、、临淄二期、、龙口、、商河、、台儿庄、、洛阳、、威、、郑州、、文登、、小涧西、、乌兰察布牟平、、沂水、、沂源、、鱼台、、章丘二期、、诸城等多个项目!。
Huaxing East's performance in Shandong province includes: Yanzhou、、Dezhou、、Dingtao、、Gaomi、、Huangdao、、Laixi、、Laizhou、、Linyi Phase II、、Linyi Lanshan、、Zibo Phase I、、Zibo Phase II、、Longkou、、Shanghe、、Taierzhuang、、Tai an、、Weihai、、Weifang、、Wendeng、、Xiaojianxi、、Yantai Muping、、Yishui、、Yiyuan、、Yutai、、Zhangqiu Phase II、、Zhucheng etc.