伟德国际官网东方承建的吉林省梅河口市生涯垃圾点火发电项目烟气净化工程通过72+24小时试运行
2024.02.23
我公司承建的吉林省梅河口市生涯垃圾点火发电项目烟气净化工程于2023年06月25日通过72+24小时试运行。。
The flue gas cleaning project of the domestic waste incineration power generation project in Meihekou City, Jilin Province, undertaken by our company, passed the 72+24 hour trial operation on June 25, 2023.
伟德国际(victor1946)官方网站-Officials Website
该项目总设计规模日点火处置生涯垃圾1200吨。。本期工程建设1条600t/d点火线,,预留1条600t/d点火线。。分两期建设。。烟气处置选取“SNCR[氨水]+半干法[Ca(OH)2浆液]+干法[Ca(OH)2]+活性炭喷射+袋式除尘+飞灰输送、、存储及不变动工艺”的烟气净化工艺,,预留SCR及湿法场地,,为我司EPC工程。。
The total design scale of this project is to incinerate 1200 tons of household waste per day. One 600t/d incineration line will be constructed in this phase of the project, and one 600t/d incineration line will be reserved. It will be constructed in two phases. The flue gas treatment adopts the flue gas purification process of "SNCR [ammonia water]+semi dry method [Ca(OH)2 slurry]+dry method [Ca(OH)2]+activated carbon injection+bag dust removal+fly ash transportation, storage and stabilization process", with reserved SCR and wet site for our EPC project.
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际官网东方在吉林省的业绩涵盖蕴含::舒兰、、梅河口、、长春农安、、长春德惠、、长春一期、、二期、、三期、、吉林、、松原等多个项目。。
Jiangsu Huaxing East’s performance in Jilin Province includes multiple projects such as Shulan, Meihekou, Changchun Nong'an, Changchun Dehui, Changchun phase I, II, and III,  Jilin, Songyuan, etc.
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
更多内容请点击或扫描下方!!
关注我们!!
Click or scan below for more information!

Follow us!

伟德国际(victor1946)官方网站-Officials Website

【网站地图】